Call for a Free Consultation (360) 891-5811

Digital Dryshack #95: P6 Status Physical % Complete

We were providing P6 training for Government Contracts at AGC San Diego, a first-class contractor and apprenticeship training facility, when we were surprised by a P6 undocumented feature. Here’s what we discovered:

  • checking ‘Use Steps to Calculate Percent Complete’ , a required setting for D.O.D. schedules, disables updating status when not using steps. (Which is the majority of the time.)
  • therefore we strongly recommend UN-checking the ‘use steps’ checkbox.

The sequence for correctly updating all Activities started but not finished (using Physical Percent Complete) follows:

  1. Check the box for Started and enter current the % Complete
  2. Manually enter Remaining Duration (this prefills the calculated Labor Resource Units and therefore cost to date)
  3. check and modify the Labor Units or % Complete if  required. (this will not affect the Remaining Duration just entered).

This simple workflow restores full autonomy to updating all 3 values exactly as desired, with the added advantage of automatically calculating the costs by entering Remaining Duration.

 

Related posts